Concrete Calculator

Length, width, thickness — and you get cubic yards, bag counts, and whether bags or a ready-mix truck is the cheaper call. Decimals welcome: 5.5" is a real spec. Typical thickness: 4" patios & walkways, 5" light driveways, 6" driveways & garages.

Concrete needed
1.23 cu yd

56 × 80 lb bags or 75 × 60 lb bags  |  order 1.36 cu yd with 10% waste

Project calculators

Fence postsBags per post & whole fence SonotubesRound form tubes by diameter Deck footingsPier footings & counts FootingsContinuous strip footings WallsFoundation & retaining walls Slab sizesPre-figured common dimensions Bags per yard45 × 80 lb = 1 yard, full table Concrete weightWhat a yard actually weighs RebarGrid, linear feet & sticks GravelYards & tons for bases StairsSolid poured steps Mix ratiosCement, sand & gravel Curing timeWalk, drive, full strength Water per bagThe strength variable PaversCount, base & bedding sand Retaining wallsBlocks, caps & base BrickBricks & mortar bags Block (CMU)Blocks & mortar Crushed stoneYards & tons by stone type SandYards & tons TopsoilYards & tons for beds MulchYards & bags AsphaltHot-mix tonnage Driveway cost2026 installed ranges

The formula, once and for all

Length (ft) × width (ft) × thickness (ft) ÷ 27 = cubic yards. Thickness in inches divided by 12 gives you feet — a 4" slab is 0.333 ft. Contractors shortcut a 4" slab as square footage ÷ 81. Both get you the same number; the calculator above just gets there faster and adds the bag math.

Common questions

How do I calculate how much concrete I need?

Multiply length × width × thickness, all in feet, then divide by 27 to get cubic yards. A 10×10 slab at 4 inches (0.333 ft) is 10 × 10 × 0.333 ÷ 27 = 1.23 cubic yards. Add 10% for waste and uneven subgrade.

How thick should a concrete slab be?

4 inches for patios, walkways, and shed pads; 5–6 inches for driveways and anything that carries vehicles; 6+ inches with reinforcement for workshops and heavy equipment.

Should I order ready-mix or buy bags?

Bags win on small jobs (under about half a cubic yard). Past one yard — about 45 × 80 lb bags — delivered ready-mix is cheaper once you count your time, and dramatically easier.

How much extra concrete should I order?

10% over the calculated volume. Subgrades are never perfectly level, and coming up short mid-pour creates a cold joint — a permanent weak line in the slab.